On November 17, Loudoun County, Virginia, is set to take a final vote on pausing new legislative data center applications for up to 12 months. The vote comes four weeks after Amazon agreed on October 20 to drop its plans to build four data centers on its 122-acre Ashburn campus, which it had purchased for around $427 million.
The same week Amazon changed its plans for Ashburn, Business Insider reported that some AWS sites had room for new Nvidia server racks but lacked adequate power to run them. As the world’s largest data center market, Loudoun County earned $1.2 billion in taxes in fiscal 2026, accounting for 39% of the county’s budget. If the vote to pause passes on November 17, new rezoning and special exception requests for data centers could take up to 12 months longer in the market. Such a delay could further affect AWS’s $578 billion backlog that is already partly unserved due to capacity constraints highlighted by Amazon CEO Andy Jassy. AWS CEO Matt Garman has cautioned that over 100 data center moratoriums are being considered across the U.S., making Loudoun County one of several instances of data center pushback.
Why Amazon Dropped Its Ashburn Data Center Plan
Amazon originally purchased the Ashburn campus for around $427.3 million in March 2026, and four months later in July the company filed a site plan called Bridgefield Tech Center, which included four two-story data center buildings spanning over 800,000 square feet in total alongside three parking garages. Amazon sought a “by-right” approval for this plan, an administrative process with no Planning Commission, public hearing or Board vote.
Two days later, on July 30, Loudon County’s Board of Supervisors’ Supervisor Juli Briskman vowed to “fight it every step of the way.” In early October, county staff told supervisors that Amazon would need additional county approval before building, citing a zoning determination that data centers were not a permitted primary use on the property.

Board Chair Phyllis Randall later announced an agreement, “Project Potomac Promise,” on October 20. Under the county’s terms, Amazon cannot construct data centers or host their supporting infrastructure on the Ashburn campus.
Finally, Amazon gave in to opposition from residents and Loudoun County supervisors, agreeing to withdraw its application to build data centers on its Ashburn campus. As part of an October 20 deal with the county, Amazon will not build data centers on the former George Washington University campus nor sue to do so. Instead, the company will seek permission to rezone the land, mainly for housing.
Neither Amazon nor Randall cited power supply as the reason for calling off the planned data center construction. For Randall, the campus was “just the wrong location for a data center,” owing to the infrastructure it would need and residents’ opposition. According to Amazon’s Josh Weissman, the company had “heard the community’s pointed concerns,” and it “took them seriously.” He added that while Amazon and the county have differing views on the site’s legal potential, it chose “a shared vision” over “costly litigation.”
Ashburn and Loudoun County’s Data Center Advantage
According to Loudoun County, it has the highest concentration of data centers worldwide, home to around 233 data center buildings and 56.5 million square feet built or under construction as of March 1, 2026, plus 35.7 million square feet approved but not yet built. In 2025, the county issued permits for the construction of over 10 million square feet of data center space, the highest in a year.
Part of the reason behind this is a 2000 zoning ruling that assigned data centers as office buildings, letting companies build them by right in office-zoned areas. Since March 2025, new data centers have required a special exception approved by a Board vote. However, projects grandfathered under the old rules can still proceed administratively.
These data centers have helped Loudoun County generate $1.2 billion in real and personal property tax revenue in fiscal 2026, contributing to 39% of its total budget. For fiscal 2027, estimated budget projects hold around 40%, at $1.3 billion.
Loudoun County Weighs a 12-Month Pause on Data Center Approvals
On September 15, Loudoun County supervisors voted 7-1-1 to pause Board consideration of certain legislative applications for data centers and electrical substations, meaning rezonings and special exceptions. The written resolution got deferred from October 20 to November 17 to give staff more time to gather additional information before the final vote. According to the county attorney, a moratorium on data center approvals would not be legal, so the county is considering a pause of up to 12 months, the longest gap Virginia law permits.
However, this pause does not cover administrative applications, including at least 17 grandfathered applications totaling over 11 million square feet. Despite the final decision, the Board can continue to consider “grid reliability” substations during the period. According to Governor Abigail Spanberger, the decision on approving or blocking data center projects should rest with the community and not the state. State Senator Russet Perry has separately drafted a three-year statewide moratorium on data center approvals.
Dominion Energy, the utility provider for Northern Virginia’s data center cluster, stated on its Q3 earnings call that it has more than 54 GW of data center capacity in various stages of contracting, including over 12 GW under electric service agreements. The company also told CBS 6 that new data centers sign 14-year contracts with minimum demand charges and post collateral of $1.5 million per MW, so residential customers don’t pay for stranded infrastructure in the event of a project falling through.
Even as Amazon Waits on Data Center Approvals, Its Nvidia Racks Wait on Power
While Amazon tackles the uncertainty after withdrawing its plans to build data centers in Ashburn, Business Insider reported that AWS has started taking ownership of Nvidia GB300 server racks under an “Early Rack Receipt Process,” even before they reach a data center. The story broke on October 20 but is based on internal emails from August.
According to this report, one email projected around $5 billion of GB300 racks in August, followed by around $3 billion a month for the foreseeable future. Some AWS sites located in the U.S. had floor spaces to store these racks but not enough available power to run them, so the finished racks were being held in intermediary warehouses. However, the report failed to provide more detail on how many racks were being stored, at which sites, and for how long.






